Demolition of N Building commenced on Monday, August 31, after several months of prepping the building for its demise.
Pablo Botello, a superintendent for Bradbury Stamm, the general contractor for the project said the demolition should take about 8 to 10 weeks to complete
Yesterday a huge excavating machine was working on knocking down a wall on the southwest corner of the building.
Botello said another excavator will soon be brought in , and that along with a bulldozer and a water truck, to keep the dust down, should be enough equipment to get the job done.  
The subcontractor performing the actual demolition work is Custom Grading of Albuquerque, Botello said.